A malfunction that shut down all of Toyota Motor's assembly plants in Japan for about a day last week occurred because some servers used to process parts orders became unavailable after maintenance procedures, the company said.
Level 1a. Stuff slightly more complicated than a list of settings, usually for something like a VFD or a stepper motor controllers. Not as common.
Level 2 PLCs, HMIs, and the black magic robotic stuff. Stand alone equipment. Like imagine a machine that can take something, heat it up, and give it to the next machine.
Level 3: DCS and SCADA. Data control center and whatever SCADA stands for, I always forget. This is typically for integrating or at least data collection of multiple stand alone equipment for level 2.
Level 4: the integration layer between Level 3 and whatever means the company has for entering in sales.
Like everything in software this is all general. Some places will mix layers, subtract layers, add them. I would complain about the inconsistent nature of it all but without it I would be unemployed
Is this specific software engineering languages? or is this electrical engineering or what kind of work is this?
Is this specific software engineering languages? or is this electrical engineering or what kind of work is this?