Knowing nothing about the process, can i ask, is the time it takes to build one based on current standards? Like if we were to focus more resources into the construction of new plants wouldnt they be built faster?
The latest nuclear power plant built in the US is seven years behind schedule and almost $20 billion over budget. It bankrupted Westinghouse Energy, and is slated to cost consumers more than double what comparable electricity costs because of these overruns.
And this was a plant that was using newer construction techniques like offsite assembly to reduce costs.
Were there mistakes during the build process like lowballing spending figures or building time so they are permitted to build or did they just royally fuck up some other way?
Knowing nothing about the process, can i ask, is the time it takes to build one based on current standards? Like if we were to focus more resources into the construction of new plants wouldnt they be built faster?
The latest nuclear power plant built in the US is seven years behind schedule and almost $20 billion over budget. It bankrupted Westinghouse Energy, and is slated to cost consumers more than double what comparable electricity costs because of these overruns.
And this was a plant that was using newer construction techniques like offsite assembly to reduce costs.
Looks like one holdup nowadays is the ability to source HALEU (Uranium that is 4x as enriched as the typical fuel used in current reactors).
https://www.energy.gov/ne/articles/what-high-assay-low-enriched-uranium-haleu
https://www.wyomingpublicmedia.org/natural-resources-energy/2022-12-14/the-opening-of-terrapowers-nuclear-plant-in-kemmerer-will-be-delayed-by-two-years
It was sourceable from Russia before they invaded Ukraine.
Were there mistakes during the build process like lowballing spending figures or building time so they are permitted to build or did they just royally fuck up some other way?
It just seems to be a general issue in the industry and not specific to this plant or the US.
Flamanville-3 in France is 5 years overrun already and is projected to be operational 12 years from now. It’s budget ballooned from 3.3B to 20B euros.
Olkiluoto-3 was only delayed a year, but the budget went from 3 to 11B Euro.
Hinkley Point C project is behind and esyimates have gone from £16B to almost £30B.